Wednesday
Apr202016

Roadwork

Wednesday
Apr202016

July 26, 2017

NOTICE as of July 26, 2017

2017 Road Program (Milling/Filling)

Various village roads will receive asphalt mill and fill, crack sealant and reclamite applications within the next 60 days. This is a moving operation with one lane traffic being maintained at all times by flagman and or Hunting Valley Police. Additional information to follow.

Shaker Blvd Culvert #13 Replacement

Shaker Blvd WILL CLOSE TO THROUGH TRAFFIC, allowing local access only, from August 7, 2017 for a 30 day period. Detour signage has been placed at this time using Fairmount Blvd as the main detour.

County Line Road

The village is working with Cuyahoga County and Geauga County regarding restoration of County Line Road from South Woodland/Route 87 north to the Gates Mills corporate line (3 mile project). County Line Road will close to through traffic, allowing local access only, starting April 1, 2018 for a reconstruction period of approximately six(6) months.